Vacuum Excavating - Specialized Services Company

Upcoming Events

April 1, 2010
Damage Prevention Utilizing Vacuum Technology

Search

Vacuum Excavating PDF Print E-mail
Project: Scottsdale Ground Water Treatment Plant
Dates: May 14, 2009 to June 16, 2009
Location: Pima Rd & Thomas Rd.
Owner: City of Scottsdale
Contractor: Keller Electrical
Description: Performed vacuum potholing to expose existing conflicts, and performed trenching for installation of conduit for utility renovation
Challenges: Lack of existing as-builts - utility conflicts
Method: Vacuum Excavating
Results:

Utilized the vacuum excavator to trench more than 600' in and outside the compound successfully avoiding existing underground utilities and allowing the contractor to safely install new wet and dry utilities for the plant.

100_1503.JPG Copy_of_100_1522.JPG 100_1501.JPG




Project: Loop 202 Widening
Dates: Ongoing since February 02, 2009
Location: Loop 202 in Phoenix and Tempe, AZ
Owner: Arizona Department of Transportation
Contractor: Kiewit-Sundt Joint Venture
Description: SSC was contracted to vacuum pothole utility conflicts along the Loop 202 construction route. In addition, SSC has performed numerous other functions utilizing the vacuum excavator, including removal of slurry from bridge columns, and assisting with pier installations.
Challenges: Locating and exposing a water main below the water table on the north side of Tempe Town Lake.
Method: Vacuum Excavating
Results: SSC is still under contract and will work with the project team until completion in late 2010.




Project: Clean up on Metro Light Rail Track
Dates: 9-13-2008 to 9-13-2008
Location: SSC crews worked over 12 hours consecutively to clear miles of track starting from the Central and McDowell Road intersection working south down 1st Avenue to Jefferson, then east to 26th Street and Washington.
Owner: City of Phoenix
Contractor: Archer Western Contractors
Description: SSC used their state-of-the art System 4000 to clear debris from track to allow Metro Light Rail to safely expand testing to the majority of its new line across the Valley.
Challenges: Two months after its initial introduction in downtown Phoenix, the Metro Light Rail began testing trains from Mesa through downtown to the intersection of Central and McDowel Road. Prior to testing however, miles of debris that had settled on the tracks during the three-year long construction process had to be cleared to avoid damage to the trains during the testing process.
Method: Vacuum Excavating
Results: If not for SSC and its unique fleet of System 4000 Vacuum Excavators, this might have been a much more difficult and time consuming process than one might think. With two Vacuum trucks in tow, SSC crews worked over 12 hours consecutively to clear 8 miles of track. With only one day remaining before testing was to commence, the crews did an amazing job that could never have been accomplished in time without the aid of the System 4000.
SSC vacuum services SSC vacuum services SSC vacuum services
 


Project: Storm Drain Locating in Mesa, AZ
Dates: 3-24-2008 to 3-25-2008
Location: Higley & McKellips
Owner: City of Mesa
Contractor: ESI Contracting
Description: ESI contracted with SSC to expose an existing storm drain that was identified using reliable as-builts and an electronic locating device, 19 ft. below the surface. An area 15 ft. x 40 ft. wide x 15 ft. deep was excavated with a trackhoe to allow the vacuum to excavate the last 4 ft. and safely expose the storm drain.
Challenges: This was a challenging project for SSC as the buried storm drain was located so far from the Vacuum truck.
Method: Vacuum Excavation
Results: Vacuum excavation utilizes 95% air at a volume of 100+ PSI and 5% water to break up soil in record time. Using the powerful air-vacuum system allowed SSC to span the distance between the system and the excavation site and expose the utility as successfully as if it had been a routine potholing project.
   
SSC vacuum services SSC vacuum services SSC vacuum services